Aquatic Complex - Les Bains des Docks

France Go Full Screen

In translation...

- Status: Built
- Location: Le Havre, France
- Dates:
Competition: April 2004
Studies: May / December 2004
Building work: January 2006 / June 2008
- Client: Mairie du Havre, CODAH
-Type of commission: Competition, winning project. Complete mission for the Aquatic Complex
- Program: Aquatic complex
- Usable Floor Area: 8600 m2
- Gross Floor Area: 12000 m2
- Budget: 16 000 000 €
- Cost m2 usable area: 1880 € / m2

Architectural team
- Project manager and partner: Mirco TARDIO
- Architects: Julie FERNANDEZ (Architect responsible for the phase Studies)
Felix MEDINA (Architect responsible for the phase Building work)
Cyril DESROCHE, Caroline DJURIC, Raphaële CARRIL, Marion DELQUEUX, Angeline FARAUD, Mathieu FOREST, Claire FREDIN, Marta GRZADZIEL, Vincent LAUREAU, Paul-Emmanuel LOIRET, Xavier LAPLAE, Vincent LAPLANTE, François LEININGER, Antony PASCUAL, Moon PUIG VILA, Arantxa MANRIQUEZ, Charlotte KHIM, Tina KORTMANN, Sophie THUILLIER, Nicolaï RAICH, Alison SADLER, Gemma SERRA, Anna STRUCK Rosemary SERRAND, Laurence SENECHAL, Antoine VAUCLARE, Qiang ZOU
- Perspectives: Didier Ghislain
- Computer graphics: Jean Angelini, Mirco Tardio, ARTEFACTORY
- Light: Odile Soudant (phase DCE)
- Mock-up: Jean-Louis Courtois

Engineers
- Structure and fluids: SERO and CET
- Economics: SLETEC, GEC

Consultant Team
- Natural and artificial light: Ingelux (studies)
- HEQ: Pierre Lefèvre, Alto, Transsolar (competition)
- Acoustics: AVEL (competition, studies)
- Scenography: Ducks Sceno (competition)
- Swimming pool: ISC (competition)